Discounted Payback Period

Discounted Payback Period

The discounted payback period is a capital budgeting procedure used to determine the profitability of a project. The shorter a discounted payback period is, means the sooner a project or investment will generate cash flows to cover the initial cost. When deciding on any project to embark on, a company or investor wants to know when their investment will pay off, meaning when the cash flows generated from the project will cover the cost of the project. A company can compare its required break-even date for a project to the point at which the project will break even according to the discounted cash flows used in the discounted payback period analysis, to approve or reject the project. The more simplified payback period formula, which simply divides the total cash outlay for the project by the average annual cash flows, doesn't provide as accurate of an answer to the question of whether or not to take on a project because it assumes only one, upfront investment, and does not factor in the time value of money. The period of time that a project or investment takes for the present value of future cash flows to equal the initial cost provides an indication of when the project or investment will break even.

The discounted payback period is used as part of capital budgeting to determine which projects to take on.

What Is the Discounted Payback Period?

The discounted payback period is a capital budgeting procedure used to determine the profitability of a project. A discounted payback period gives the number of years it takes to break even from undertaking the initial expenditure, by discounting future cash flows and recognizing the time value of money. The metric is used to evaluate the feasibility and profitability of a given project.

The more simplified payback period formula, which simply divides the total cash outlay for the project by the average annual cash flows, doesn't provide as accurate of an answer to the question of whether or not to take on a project because it assumes only one, upfront investment, and does not factor in the time value of money.

The discounted payback period is used as part of capital budgeting to determine which projects to take on.
More accurate than the standard payback period calculation, the discounted payback period factors in the time value of money.
The discounted payback period formula shows how long it will take to recoup an investment based on observing the present value of the project's projected cash flows.
The shorter a discounted payback period is, means the sooner a project or investment will generate cash flows to cover the initial cost.

Understanding the Discounted Payback Period

When deciding on any project to embark on, a company or investor wants to know when their investment will pay off, meaning when the cash flows generated from the project will cover the cost of the project.

This is particularly useful because companies and investors usually have to choose between more than one project or investment, so being able to determine when certain projects will pay back compared to others makes the decision easier.

The basic method of the discounted payback period is taking the future estimated cash flows of a project and discounting them to the present value. This is compared to the initial outlay of capital for the investment.

The period of time that a project or investment takes for the present value of future cash flows to equal the initial cost provides an indication of when the project or investment will break even. The point after that is when cash flows will be above the initial cost.

The shorter a discounted payback period is means the sooner a project or investment will generate cash flows to cover the initial cost. A general rule to consider when using the discounted payback period is to accept projects that have a payback period that is shorter than the target timeframe.

A company can compare its required break-even date for a project to the point at which the project will break even according to the discounted cash flows used in the discounted payback period analysis, to approve or reject the project.

Calculating the Discounted Payback Period

To begin, the periodic cash flows of a project must be estimated and shown by each period in a table or spreadsheet. These cash flows are then reduced by their present value factor to reflect the discounting process. This can be done using the present value function and a table in a spreadsheet program.

Next, assuming the project starts with a large cash outflow, or investment to begin the project, the future discounted cash inflows are netted against the initial investment outflow. The discounted payback period process is applied to each additional period's cash inflow to find the point at which the inflows equal the outflows. At this point, the project's initial cost has been paid off, with the payback period being reduced to zero.

Payback Period vs. Discounted Payback Period

The payback period is the amount of time for a project to break even in cash collections using nominal dollars. Alternatively, the discounted payback period reflects the amount of time necessary to break even in a project, based not only on what cash flows occur but when they occur and the prevailing rate of return in the market.

These two calculations, although similar, may not return the same result due to the discounting of cash flows. For example, projects with higher cash flows toward the end of a project's life will experience greater discounting due to compound interest. For this reason, the payback period may return a positive figure, while the discounted payback period returns a negative figure.

Example of the Discounted Payback Period

Assume that Company A has a project requiring an initial cash outlay of $3,000. The project is expected to return $1,000 each period for the next five periods, and the appropriate discount rate is 4%. The discounted payback period calculation begins with the -$3,000 cash outlay in the starting period. The first period will experience a +$1,000 cash inflow.

Using the present value discount calculation, this figure is $1,000/1.04 = $961.54. Thus, after the first period, the project still requires $3,000 - $961.54 = $2,038.46 to break even. After the discounted cash flows of $1,000 / (1.04)2 = $924.56 in period two, and $1,000/(1.04)3 = $889.00 in period three, the net project balance is $3,000 - ($961.54 +$924.56 + $889.00) = $224.90.

Therefore, after receipt of the fourth payment, which is discounted to $854.80, the project will have a positive balance of $629.90. Therefore, the discounted payback period is sometime during the fourth period.

Related terms:

Cash Flow

Cash flow is the net amount of cash and cash equivalents being transferred into and out of a business. read more

Compound Interest , Formula, & Calculation

Compound interest is the interest on a loan or deposit that accrues on both the initial principal and the accumulated interest from previous periods. read more

Conventional Cash Flow

Conventional cash flow is a series of inward and outward cash flows over time in which there is only one change in the cash flow direction.  read more

Discounted Cash Flow (DCF)

Discounted cash flow (DCF) is a valuation method used to estimate the attractiveness of an investment opportunity. read more

Discount Rate

"Discount rate" has two distinct definitions. I can refer to the interest rate that the Federal Reserve charges banks for short-term loans, but it's also used in future cash flow analysis. read more

Managerial Accounting

Managerial accounting is the practice of analyzing and communicating financial data to managers, who use the information to make business decisions. read more

Net Present Value (NPV)

Net Present Value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows over a period of time. read more

Outlay Cost

An outlay cost is a direct cost incurred in order to execute a strategy, complete a project, or acquire an asset. read more

Payback Period

The payback period refers to the amount of time it takes to recover the cost of an investment or how long it takes for an investor to hit breakeven. read more

Present Value – PV

Present value is the concept that states an amount of money today is worth more than that same amount in the future. In other words, money received in the future is not worth as much as an equal amount received today. read more