Cost-Plus Contract

Cost-Plus Contract

A cost-plus contract is an agreement to reimburse a company for expenses incurred _plus_ a specific amount of profit, usually stated as a percentage of the contract’s full price. 4. **Cost-plus percent-of-cost contracts*allow the amount of reimbursement to rise if the contractor's costs rise. The pros and cons of using these types of contracts include the following: They eliminate some risk for the contractor. They allow the focus to shift from the overall cost to the quality of work being done. They cover all the expenses related to the project, so there are no surprises. They may leave the final cost up in the air since they can't be predetermined. Cost-plus contracts can be contrasted with fixed-cost contracts, in which two parties agree up front to a specific cost regardless of the actual expenses incurred by the contractor. A cost-plus contract is an agreement to reimburse a company for expenses incurred _plus_ a specific amount of profit, usually stated as a percentage of the contract’s full price. In a cost-plus contract, one party agrees to reimburse the contracting party for expenses plus a specified profit proportional to the full value of the contract.

In a cost-plus contract, one party agrees to reimburse the contracting party for expenses plus a specified profit proportional to the full value of the contract.

What Is a Cost-Plus Contract?

A cost-plus contract is an agreement to reimburse a company for expenses incurred plus a specific amount of profit, usually stated as a percentage of the contract’s full price. These type of contracts are primarily used in construction where the buyer assumes some of the risk but also provides a degree of flexibility to the contractor. In such a case, the party drawing up the contract anticipates that the contractor will make good on his or her promises to deliver, and agrees to pay extra so that the contractor can make additional profit upon completion.

Cost-plus contracts can be contrasted with fixed-cost contracts, in which two parties agree up front to a specific cost regardless of the actual expenses incurred by the contractor. Cost-plus contracts may also be known as cost-reimbursement contracts.

In a cost-plus contract, one party agrees to reimburse the contracting party for expenses plus a specified profit proportional to the full value of the contract.
Cost-plus contracts are often used in construction when the budget is restricted or when there is a high probability that actual costs might be less than anticipated.
Contractors must provide proof of all related expenses, including direct and indirect costs.

Understanding Cost-Plus Contracts

Cost-plus contracts are generally used if the party drawing up the contract has budgetary restrictions or if the overall scope of the work can't be properly estimated in advance.

In construction, cost-plus contracts are drawn up so contractors can be reimbursed for almost every expense actually incurred on a project. The cost-plus contract pays the builder for direct costs and indirect or overhead costs. All expenses must be supported by documentation of the contractor’s spending in the form of invoices or receipts. The contract moreover allows the contractor to collect a certain amount above the reimbursed amount, so he or she may be able to make a profit — hence, the "plus" in cost-plus contracts.

Some contracts may limit the amount of reimbursement, so not every expense would be covered. This is especially true if the contractor makes an error during the course of the project or is found to be negligent in any part of the construction.

Cost-plus contracts are also used in research and development (R&D) activities, where a larger company may outsource R&D activities to a smaller firm, such as large pharmaceutical company contracting to the lab of a small biotech company. The U.S. government also uses cost-plus contracts with military defense companies that develop new technologies for national defense.

Governments generally prefer cost-plus contracts because they can choose the most qualified contractors instead of the lowest bidder.

Types of Cost-Plus Contracts

Cost-plus contracts can be separated into four categories. They each allow for the reimbursement of costs as well as an additional amount for profit:

  1. Cost-plus award fee contracts allow the contractor to be awarded a fee usually for good performance.
  2. Cost-plus fixed-fee contracts cover both direct and indirect costs, in addition to a fixed fee.
  3. Cost-plus incentive fee contracts happen when the contractor is given a fee if his or her performance meets or exceeds expectations.
  4. Cost-plus percent-of-cost contracts allow the amount of reimbursement to rise if the contractor's costs rise.

Advantages and Disadvantages of Using Cost-Plus Contracts

The pros and cons of using these types of contracts include the following:

Example of How a Cost-Plus Contract Works

Assume ABC Construction Corp. has a contract to build a $20 million office building, and the agreement states that costs cannot exceed $22 million. ABC’s profit is agreed at 15% of the contract’s full price of $3 million. Additionally, ABC Construction is eligible for an incentive fee if the project is completed within nine months.

ABC must submit dated receipts for all expenses, and the client will inspect the job site for quality to verify that specific components are completed to specification such as the plumbing, electrical, fixtures, etc. The contract allows ABC to incur direct costs such as materials, labor, and costs incurred to hire subcontractors. ABC can also bill indirect, or overhead, costs, which include insurance, security, and safety. The contract states that overhead costs are billed at $50 per labor-hour.

Special Consideration: Percentage of Completion in a Cost-Plus Contract

The above project uses the percentage of completion process to account for-profit and to submit bills to the client, and the contract provides specific percentages for billing.

Assume, for example, that ABC can bill for 20% of the full contract price once 20% of the materials are purchased, and the client verifies the concrete foundation is in place. At that point, ABC sends an invoice for 20% of the $20-million contract at $4 million, and posts 20% of the firm’s profit, or $600,000, to the financial statements.

Related terms:

Administrative Expenses

Administrative expenses are the costs an organization incurs not directly tied to a specific function such as manufacturing, production, or sales. read more

Contractor Fraud

Contractor fraud refers to illegal business practices committed by individual contractors or firms hired to renovate, repair or (re)build residential properties. read more

Contributory Negligence

Contributory negligence is the plaintiff's failure to demonstrate care for their own safety. Often, defendants use contributory negligence as a defense. read more

Incentive Fee

An incentive fee is a fee charged by a fund manager based on a fund's performance over a given period and is usually compared to a benchmark. read more

Independent Contractor

An independent contractor is a person or entity engaged in a work performance agreement with another entity as a non-employee. read more

Mandatory Binding Arbitration

Mandatory binding arbitration requires the parties to resolve contract disputes before an arbitrator rather than through the court system. read more

Mergers and Acquisitions (M&A)

Mergers and acquisitions (M&A) refers to the consolidation of companies or assets through various types of financial transactions. read more

Overhead

Overhead refers to the ongoing business expenses not directly attributed to creating a product or service. read more

Progress Billings

Progress billings are invoices requesting payment for work completed to date. They are prepared and submitted for payment at different stages in the process of a major project. read more

Research and Development (R&D)

Research and development (R&D) is a term to describe the effort a company devotes to the innovation, and improvement of its products and processes. read more